Burnham RTC (Return Temperature Control) Instalační manuál Strana 14

  • Stažení
  • Přidat do mých příruček
  • Tisk
  • Strana
    / 60
  • Tabulka s obsahem
  • KNIHY
  • Hodnocené. / 5. Na základě hodnocení zákazníků
Zobrazit stránku 13
14 of 60
On multiple boiler applications, each boiler is installed in the same arrangement as a single boiler application. Each boiler loop contains
its own boiler circulator, diverting valve and actuator, RTC control, and return sensor. A number of different boiler sequencers can be
used in conjunction with the RTC by energizing the control’s heat demand circuit. The RTC control’s outdoor reset feature cannot be
used on multiple boiler installations. The sequencer’s outdoor reset feature (if available) would have to be utilized instead.
5
Boil
Pm
p
Po
we
r
6
N
3
L
120 V (ac)
N
L
4
N
1
Heat
Demand
2
24 to 240 V (ac)
N
L
Powered Input Connections
120 V (ac) Power
Connect the 120 V (ac) power supply to the Power L and Power N terminals (3 and 4).
This connection provides power to the microprocessor and display of the control. As
well, this connection provides power to the Boil Pmp terminal (5). The control should
be powered from a dedicated circuit. This avoids power disruption to the control in
the event of failure on another electrical device on the same circuit. DO NOT power
the control from the boiler or burner circuit, since there may be times where the
boiler or burner circuit may be switched off in the summer. This would prevent the
exercising of the boiler recirculating pump and the diverting valve. Boiler protection
for dormant boilers, in a multiple boiler application, will not be possible if the control
is not powered.
Heat Demand
To generate a heat demand, a voltage between 24 V (ac) and 240 V (ac) must be
applied across the Heat Demand terminals (1 and 2).
Output Connections
Boiler Recirculating Pump Contact (Boil Pmp)
The Boil Pmp output terminal (5) on the control is a powered output. When the relay in
the control closes, 120 V (ac) is provided to the Boil Pmp terminal (5) from the Power L
terminal (3). To operate the boiler recirculating pump, connect one side of the boiler
recirculating pump circuit to terminal (5), and the second side of the pump circuit to
the neutral (N) terminal (6).
Po
we
r
4
120 V (ac)
L
N
3
STEP FOUR
ROUGH-IN WIRING
All electrical wiring terminates in the control base wiring chamber. The base has standard
7
/8(22 mm) knockouts, which accept
common wiring hardware and conduit fittings. Before removing the knockouts, check the wiring diagram and select those sections
of the chamber with common voltages. Do not allow the wiring to cross between sections, as the wires will interfere with safety
dividers, which should be installed at a later time.
Power must not be applied to any of the wires during the rough-in wiring stage.
- All wires are to be stripped to a length of 3/8 in (9 mm) to ensure proper connection to the control.
- If a Mix Sensor 071 or an Outdoor Sensor 070 is used, install the sensor according to the installation instructions in the Data
Brochure D 070 and run the wiring back to the control.
- Make sure the Boiler Return Sensor is installed and run the wiring back to the control.
- Run wire from other system components (pumps, boilers, etc.) to the control.
- Run wires from the 120 V (ac) power to the control. Ideally, a separate dedicated circuit should power the control.
- Use a clean power source with a 15 A circuit to ensure proper operation. Multi-strand 16 AWG wire is recommended for all
120 V (ac) wiring due to its superior flexibility and ease of installation into the terminals.
STEP FIVE
ELECTRICAL CONNECTIONS TO THE CONTROL
The installer should test to confirm that no voltage is present at any of the wires. Push the control into the base and slide it down
until it snaps firmly into place.
Zobrazit stránku 13
1 2 ... 9 10 11 12 13 14 15 16 17 18 19 ... 59 60

Komentáře k této Příručce

Žádné komentáře